Draft a delay notice without missing the contract clauses
Not legal advice. This guide is general information, not legal advice. Your contract controls. Have someone who knows the contract, or a lawyer, review any notice before you send it.
Get a clean, factual first draft of a notice of delay, then make sure it meets your contract's rules.
Tools
A general AI assistant, plus your actual contract.
Steps
- Find the notice clause in your contract: the deadline, who receives it, how it must be delivered, and what it must contain.
- Paste that clause, with a factual timeline, into the Schedule delay notice prompt.
- Compare the draft to the clause line by line.
- Have someone who knows the contract (or counsel) review it.
- Send it on time, by the method the contract requires, and keep proof of delivery.
The prompts
Schedule delay notice
Draft a formal notice of delay from a general contractor. To: [owner/architect] Project: [name or generic] Contract notice clause (paste if available): [text] Delay event: [what happened, when it started] Cause and responsibility: [e.g., late owner decision, unforeseen condition, weather] Activities affected / critical path impact: [details] Estimated delay: [days, or "TBD, will update"] Mitigation we're taking: [actions] Tone: professional and factual. Reserve rights to time and cost. State that a detailed impact analysis will follow.Full prompt page →
Change order narrative
Write a change order narrative for owner/architect review. Contract: [GC agreement type, relevant clause if known] What changed: [description] Cause: [owner request / design error / unforeseen condition / RFI #] Supporting docs: [RFI, ASI, bulletin, field photos, dates] Cost: [amount + brief breakdown] Schedule impact: [days or none] Format: Background, Description of Change, Reason/Entitlement, Cost Summary, Schedule Impact, Attachments list. Factual, non-adversarial, easy for a non-builder owner to follow.Full prompt page →
Checklist before you send
- Sent within the contract's notice window
- Addressed to the parties the contract names
- Delivered by the required method
- Reserves rights to time and cost
- Says that an impact analysis will follow
What AI should NOT do here
- Interpret your contract or decide entitlement
- Replace legal review
- Make up dates or schedule impacts